Milleproroghe Decree – Further Extension of Time Limits for Building Permits and Urban Planning Agreements

Following the latest amendment to the “Milleproroghe” Decree (Decree-Law No. 200/2025), recently approved by the Constitutional Affairs and Budget Committees of the Chamber of Deputies, the special regime introduced by the “Ukraine Decree” in 2022 to support the construction sector, affected by increased material costs and supply chain disruptions, has been further extended.

The new amendment, which will enter into force only upon approval of the conversion law and its publication in the Official Gazette, extends the favourable regime to all building permits and other authorisations issued or perfected by 31 December 2025.

In addition, the extended validity period for the commencement and completion of works is increased from 36 to 48 months, resulting in an overall extension of up to four years beyond the ordinary statutory time limits provided under the Consolidated Building Act (Presidential Decree No. 380/2001).

The extension applies to the main building titles and authorisations, including:

(i) building permits;

(ii) certified notifications of commencement of works (SCIA);

(iii) landscape authorisations;

(iv) environmental authorisations and declarations, however named;

(v) implementation plans.

Certain conditions remain applicable: the relevant time limits must not have already expired at the time of notification of the intention to benefit from the extension, and the building titles must comply with newly adopted urban planning instruments.